Veligonda first phase will be completed by June: Minister

‘Water will flow into the fields from the project from kharif next’

November 30, 2019 07:45 pm | Updated 07:45 pm IST - ONGOLE

Water Resources Minister P. Anil Kumar during his inspection of the Veligonda project, near Dornala, in Prakasam district on Saturday.

Water Resources Minister P. Anil Kumar during his inspection of the Veligonda project, near Dornala, in Prakasam district on Saturday.

The first phase of the ₹6,492-crore Pula Subbaiah Veligonda project, one of the fast-track projects taken up by former Chief Minister Y.S. Rajasekhara Reddy under the ‘Jalayagnam’ programme, will be completed by June next at any cost, Water Resources Minister P. Anil Kumar has said.

Inspecting the ongoing works at the project site along with his Cabinet colleagues Balineni Srinivasa Reddy and A. Suresh, he said that the YSRCP government was according top priority to the Polavaram and the Veligonda projects.

“Water will flow into the fields from the Veligonda project from kharif next,” the Minister asserted.

“In six months, Chief Minister Y.S. Jagan Mohan Reddy has bettered the good governance provided by his father Rajasekhara Reddy.”

Reverse bidding

The YSRCP government saved ₹62.1 crore of public money on Tunnel II of the project through the reverse bidding process after cancelling the contract awarded by the TDP regime for ₹553.13 crore, he said.

The second phase envisaged drawing 32.80 tmcft water to irrigate 3.28 lakh acres and provide drinking water to 11.25 lakh people.

Mr. Anil Kumar directed the officials to speed up the tunnel work from both sides and also complete the canal lining work by January itself.

Under the first phase, Krishna water will be provided to 1.19 lakh acres and drinking water to 4 lakh people.

Rehab package

Mr. Jagan Mohan Reddy was considering giving a better rehabilitation package to the 4,617 displaced families in 11 villages, Mr. Suresh said.

Touted as an engineering marvel with two giant tunnels to draw Krishna water from the foreshore of the Srisailam reservoir without disturbing the habitat of wild animals in the Nagarjunasagar Srisailam Tiger Reserve(NSTR), the project had suffered time and cost overruns as drilling of the twin tunnels proved to be a herculean task.

“So far, ₹5106.80 crore has been spent on the project,” officials said.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.